Complex Workover Operations in Qalmaz and Garadagh Fields (51 Wells)

Complex Workover Operations in Qalmaz and Garadagh Fields (51 Wells)

Project information

  • Category Tikinti işləri
  • Date 30 November 2024

Complex Workover Operations in Qalmaz and Garadagh Fields (51 Wells)

Between May 25 and November 30, 2024, complex workover and well integrity operations were carried out on 33 wells in KaradagUGS and 18 wells in Qalmaz UGS. The operations were successfully completed with 14 WO rigs and 4 CTUs under high reservoir pressures.