Workover Operations in Qalmaz and Garadagh Fields (147 Wells)
Rehabilitation and well integrity operations conducted with 107 wells in Qalmaz and 40 wells in Karadag UGS fields from November 7, 2025 to May 25, 2024.. All work was successfully completed under high injection and withdrawal pressures using 14 WO rigs and 4 Coil Tubing Units (CTUs). Operations included well logging, testing, cleaning, new and repeat perforations, packer installation, and installation of subsurface and surface safety valves with control systems.